The Burn Repair Continued...


This week, with the new monolithic support beams in place, we began framing the attic. Some of the rafters we installed were over 30’ in length. We hoisted the new rafters into place and bolted them into place. The overall area that we are framing is 4,500 square feet. Once the rafters are in place and properly supported we will apply the roof decking substrate.